How Long Does a Bathroom Remodel Take? A Realistic Chicago Timeline
Ivan Koconda Avatar

It’s the first question on every bathroom project, and the hardest to answer honestly with a single number — because a bathroom remodel isn’t one job, it’s a sequence of jobs that have to happen in order, with inspections, deliveries, and curing time in between. What a contractor can do is show you the sequence, tell you which phases run long and why, and flag the decision points where your project can gain or lose a week. Here’s how a full bathroom remodel with Lux Renovations actually unfolds in Chicago.

A typical full bathroom remodel with us runs about 3 weeks at the entry level, 4–7 weeks for a mid-level renovation, and 6–10 weeks for a fully custom project. That range assumes the phases below go in order without a major surprise — read on for what stretches it.

Before anyone picks up a hammer: design, selections, and ordering

The clock starts well before demolition. Tile, the vanity, fixtures, glass hardware, and any specialty items — a steam unit, a wall-hung toilet and its carrier, a drop-in tub — all have to be selected, and most have to be ordered. Lead times are the quiet schedule-killer in remodeling: work can’t start on a shower whose valve hasn’t arrived, and tile installation can’t begin with tile still on a truck. At Lux, Ivan Koconda consults on design and finish material selections up front, and where finish materials are structured as allowances in the contract, selections get made against that budget early. Clients who buy their own fixtures through our supplier connections should treat their delivery dates as their responsibility — a late vanity holds up everything behind it.

Permits and, for condos, building approval

Chicago projects need permits for plumbing and electrical work, and Evanston and North Shore suburbs run their own processes. If your bathroom is in a high-rise condo, add the building’s layer on top: management approval of the scope, certificates of insurance, elevator reservations, and the building’s rules on work hours and workdays. None of this is difficult, but it is sequential — approval comes before demolition, not during — and a realistic timeline accounts for it instead of discovering it in week one.

Demolition

Demo is the fast, loud phase: fixtures out, tile and substrate out, down to the framing and the plumbing. It’s also the moment of truth. Rot behind a shower wall, tired supply lines, or a subfloor that’s seen water — this is when hidden conditions show themselves, and honest timelines leave a little room for what demo reveals.

Rough plumbing and electrical

With the room open, the rough work goes in: drains, supply lines, and vents set for the new layout; the shower valve and any steam or tub plumbing placed; electrical run for lighting, the exhaust fan, and upgrades like heated floors. If fixtures moved, this phase is longer. If the layout stayed put, it’s mostly replacement and updating.

Inspections

Rough work gets inspected before anything is closed up. Inspection scheduling is outside any contractor’s control — the work has to be ready when the inspector comes, and the wall can’t close until it passes. Good contractors build inspection days into the sequence rather than treating them as delays; they’re a normal, planned part of the order of operations.

Waterproofing and tile: the long pole

This is the phase that sets the pace of the whole back half of the project. The shower gets its waterproofing system; floors get their prep — including radiant heat mats if you’ve added heated floors; then tile goes on, floor and shower walls. Large-format tile (we install a lot of 36×36, 48×48, and 24×48) demands a flat substrate and careful setting, and then everything has to cure: mortar before grout, grout before the shower is sealed and used. Curing time isn’t a contractor being slow — it’s chemistry, and skipping it is how showers fail early. Expect tile to be the longest single stretch of the project, and be suspicious of any timeline where it isn’t.

Lux Renovations bathroom remodel with blue tile shower and wood vanity

Glass: measured after tile, on purpose

Shower glass can’t be ordered until the tile is finished, because it’s measured off the actual finished opening — tile thickness and all. Measuring earlier would mean guessing, and custom glass doesn’t forgive guesses. So there’s a built-in fabrication wait between “tile done” and “glass installed,” during which the rest of the room keeps moving. First-time remodelers often read this gap as a delay; it’s the correct sequence, and your contractor should tell you about it before the project starts, not after.

Fixtures, trim, and paint

The finish phase brings the room back: vanity set — double wood vanities are a frequent choice in our master baths — toilet installed, tub trim and shower fixtures on, lighting up, the Panasonic Whisper exhaust fan connected, mirrors and accessories, then paint and final caulking. It’s many small tasks rather than one big one, and it’s where the room stops looking like a job site.

Lux Renovations bathroom remodel with wood vanity and round mirror

Final walkthrough

The project ends with a walkthrough with Ivan: every fixture run, every drawer and door checked, grout lines and paint reviewed, and any touch-ups noted and handled. That’s the handover — and because Ivan is the estimator and project manager on the same job, there’s no “the other guy promised that” at this stage. The person walking the room with you priced it and ran it.

What actually stretches a timeline

The usual suspects, in rough order: material delays and late selections; change orders mid-project (moving a fixture after rough-in means redoing rough-in); inspection scheduling; hidden conditions found at demo; and condo building rules that compress work into set hours and days. Weather rarely matters indoors — decisions and deliveries do.

How Lux manages it

Lux Renovations is a licensed General Contractor and insured. Every project runs through one point of contact — Ivan, founder, owner, estimator, and project manager — who coordinates the trades, the architects and suppliers where they’re involved, the permits, and the building management, and structures payments in milestones tied to the phases above, so the schedule and the money move together. That single-thread management is a big part of how we’ve earned a 5.0-star rating across 36 Google reviews — and the sequencing in this article isn’t theory: it’s the same order we followed on the real master bath behind our post “7 Bathroom Remodeling Tips From a Real Lux Master Bath.”

Thinking about a bathroom remodel and want a timeline built around your building and your selections — not a template? Call Ivan at (773) 999-2822 or Ned at (773) 554-4844, or start at luxrenovations.net/become-a-client/.